Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin Exam CDCP Topic 1 Question 12 Discussion

Actual exam question for Exin's Certified Data Centre Professional Exam exam
Question #: 12
Topic #: 1
[All Certified Data Centre Professional Exam Questions]

What should be considered when implementing hot- or cold-aisle containment in an existing computer room?

Show Suggested Answer Hide Answer
Suggested Answer: C

Hot- or cold-aisle containment is a strategy to improve the cooling efficiency and reduce the energy consumption of data centers by isolating the hot exhaust air from the cold supply air. However, implementing this strategy in an existing computer room may create potential issues with the existing fire suppression system(s), such as:

* The containment barriers may interfere with the distribution and activation of the fire suppression agents, such as water, gas, or aerosol, and reduce their effectiveness in extinguishing a fire.

* The containment barriers may create pockets of high temperature and pressure that could damage the equipment or the containment structure itself in the event of a fire.

* The containment barriers may obstruct the access and visibility of the fire detection and alarm devices, such as smoke detectors, heat sensors, or manual call points, and delay the response time of the fire suppression system(s).

* The containment barriers may violate the local fire codes and regulations that specify the minimum clearance and ventilation requirements for the data center.

Therefore, when implementing hot- or cold-aisle containment in an existing computer room, it is important to consider the impact on the existing fire suppression system(s) and take appropriate measures to ensure the safety and compliance of the data center, such as:

* Consulting with the fire authorities and the fire suppression system vendor to assess the compatibility and suitability of the containment solution with the existing fire suppression system(s).

* Modifying or upgrading the existing fire suppression system(s) to accommodate the containment solution, such as relocating or adding fire suppression devices, adjusting the discharge rate and pressure, or installing a secondary fire suppression system within the contained area.

* Installing fire-rated containment barriers that can withstand high temperatures and resist the spread of fire and smoke, and that have self-closing or automatic release mechanisms in case of a fire.

* Installing fire detection and alarm devices within the contained area and ensuring their proper integration and communication with the existing fire suppression system(s).

* Conducting regular testing and maintenance of the fire suppression system(s) and the containment solution to ensure their functionality and reliability.


Contribute your Thoughts:

Francene
4 months ago
Yeah, all points are valid. But fire suppression issues could be a deal-breaker!
upvoted 0 times
...
Raul
4 months ago
Also, A makes sense. Equipment overheating at the back of the rack could be problematic.
upvoted 0 times
...
Sabrina
4 months ago
True, but don't forget about D. Cabling can get really tricky in a contained area.
upvoted 0 times
...
Cheryl
5 months ago
I think option C, potential issues with the fire suppression system, is a big concern.
upvoted 0 times
...
Francene
5 months ago
Definitely a tough one. What should be considered?
upvoted 0 times
...
Hubert
5 months ago
What do you all think about the exam question on hot- and cold-aisle containment?
upvoted 0 times
...

Save Cancel