Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin Exam ASM Topic 9 Question 47 Discussion

Actual exam question for Exin's ASM exam
Question #: 47
Topic #: 9
[All ASM Questions]

After the creation of the Release Plan, the Product Owner says:

Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel