BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin Exam ASF Topic 5 Question 71 Discussion

Actual exam question for Exin's ASF exam
Question #: 71
Topic #: 5
[All ASF Questions]

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.

What is the most likely reason that the team did not meet the Sprint objectives?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

An
1 months ago
But what if the team is over-worked? Maybe they couldn't handle the workload without that key member.
upvoted 0 times
...
Reita
1 months ago
D) The team is over-worked. Losing a key member for two days in a four-week Sprint is bound to take a toll, even on the most dedicated team.
upvoted 0 times
...
Marvel
1 months ago
I agree with Sherell. If they had a key member missing at the beginning, they should have adjusted their plan.
upvoted 0 times
...
Nakita
2 months ago
I bet the team member who fell ill was the one who always brings the doughnuts. No wonder they couldn't focus!
upvoted 0 times
Rene
28 days ago
C: Yeah, they should have adjusted their plan to accommodate the missing member.
upvoted 0 times
...
Brice
1 months ago
B: It's possible that the team didn't plan for unexpected events like this.
upvoted 0 times
...
Chaya
1 months ago
A: Maybe the team should have re-prioritized tasks when the member fell ill.
upvoted 0 times
...
...
Dalene
2 months ago
B) The team is lacking skills. Losing a key member for two days is a significant setback, so the team may not have had the necessary skills to compensate.
upvoted 0 times
Cherelle
13 days ago
D) The team is over-worked.
upvoted 0 times
...
Marisha
21 days ago
C) The team did not plan the Sprint effectively.
upvoted 0 times
...
Trevor
23 days ago
B) The team is lacking skills.
upvoted 0 times
...
Linn
25 days ago
A) The Product Owner is unable to prioritize.
upvoted 0 times
...
...
Wilford
2 months ago
C) The team did not plan the Sprint effectively. With a key member out for two days, the team should have adjusted their plans accordingly.
upvoted 0 times
Belen
1 months ago
B: Yeah, they could have redistributed the work to other team members.
upvoted 0 times
...
India
1 months ago
A: The team should have re-planned when the key member fell ill.
upvoted 0 times
...
...
Sherell
2 months ago
I think the team did not plan the Sprint effectively.
upvoted 0 times
...

Save Cancel