Exin Exam ASF Topic 12 Question 31 Discussion

Actual exam question for Exin's ASF exam
Question #: 31
Topic #: 12
[All ASF Questions]

During a Sprint Planning session, the team argues about the work estimates for a particular story.

The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?

Show Suggested Answer Hide Answer
Suggested Answer: C