As the CISO, you are the project sponsor for a highly visible log management project. The objective of the project is to centralize all the enterprise logs into a security information and event management (SIEM) system. You requested the results of the performance quality audits activity.
The performance quality audit activity is done in what project management process group?
Currently there are no comments in this discussion, be the first to comment!