Dell Exam DCPPE-200 Topic 4 Question 2 Discussion

Actual exam question for Dell's DCPPE-200 exam
Question #: 2
Topic #: 4
[All DCPPE-200 Questions]

An engineer is inventorying a newly arrived M1000e shipment that will be used for a virtual environment. The inventory includes the following:

Blade Server Enclosure, M1000E, PowerEdge -- qty 1

Power Supplies 2700W High Efficiency -- qty 3

Redundant Chassis Management Controller- qty 1

Power Cords, QTY3, 8FT, C19/C20 for M1000E Server Blade Chassis -- qty 2

Cat5e Patch Cable 1000Mb -- qty 2

Dell Force10 MXL 10/40 GbE DCB Blade Switch -- qty 2

QSFP+ 40GbE Module, 2 port, Hot Swap -- qty2

SFP+ 10GbE Module, 4 port, Hot Swap -- qty 2

SFP+ to SFP+, 10GbE, Copper Twinax Direct Attach cable, 3 Meters -- qty 8

The chassis power will be set for grid redundancy. The top of rack switches are 10Gb and the management switch is 1000 Base-T. What is missing from this inventory that is needed to accomplish this task?

Show Suggested Answer Hide Answer
Suggested Answer: A