A technical architect is helping a customer prepare for a data center maintenance window All applications must failover to the disaster recovery site The customer also wants to test their disaster recovery plan

What PowerStore Manager replication option should be used to address the customer's need: and from which site should the option be run?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Adelle
6 months ago
I think the customer should consider option D, Failover from source site, as it might provide better control over the failover process.
upvoted 0 times
...
Larae
6 months ago
I agree with Charlene, option A seems like the best choice for testing the disaster recovery plan.
upvoted 0 times
...
Charlene
6 months ago
But wouldn't it make more sense to failover from the target site to ensure smooth transition?
upvoted 0 times
...
Mary
6 months ago
I disagree, I believe option B, Planned failover from source site, would be more appropriate.
upvoted 0 times
...
Charlene
6 months ago
I think the customer should use option A, Planned failover from target site.
upvoted 0 times
...