In addition to the Final Test Plan and Customer Satisfaction Survey, what document/form is required to be signed by the customer at the Project Closure Meeting?
Final Project Signoff is the way to go. It's the official stamp of approval from the customer. Anything else and they might as well just high-five the project manager and call it a day.
The Final Project Signoff is definitely the correct answer here. It's the document that officially closes out the project and acknowledges the customer's satisfaction.