CompTIA Exam PK0-005 Topic 4 Question 20 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 20
Topic #: 4
[All PK0-005 Questions]

A PM is working on the preliminary scope statement and identifies that this project has the same approach as another project that was completed last year. Which of the following actions would the PM most likely perform?

Show Suggested Answer Hide Answer
Suggested Answer: B

This is where an existing application that is highly utilized by clients is moving to a new release, as it involves deploying and operating it in a live environment.Reference= CompTIA Project+ Study Guide1, Chapter 4: Project Environments


Contribute your Thoughts:

Using existing artifacts and accommodating based on the current project success criteria is the most logical approach. It saves time and leverages previous learnings.
upvoted 0 times
...
Armanda
7 days ago
I think the PM should use existing artifacts and accommodate based on current project success criteria.
upvoted 0 times
...