After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: D

A RACI chart would be the most useful option for the project manager to illustrate roles for major project activities for an upcoming project kickoff. A RACI chart is a visual representation of a RACI matrix that shows who is responsible, accountable, consulted, and informed for each task or activity in a project using a table format. A RACI chart can help to communicate and document the roles and expectations of each team member and stakeholder for the project and ensure alignment and agreement.


Contribute your Thoughts:

Glenna
2 days ago
But what if we lose the candidate and delay the project even more?
upvoted 0 times
...
Tori
4 days ago
I think we should withdraw the offer to the candidate and raise this as a risk.