Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 3 Question 37 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 37
Topic #: 3
[All PK0-005 Questions]

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

Show Suggested Answer Hide Answer
Suggested Answer: C

Agile methodologies emphasize flexibility and iterative progress, so strict deadlines can be a concern. They may limit the team's ability to adapt and respond to change, as emphasized by CompTIA Project+ in agile project management principles.


Contribute your Thoughts:

Kent
1 months ago
C is the obvious choice here. Stakeholders and their deadlines are like the Grim Reaper of Agile. Run, project manager, run!
upvoted 0 times
Venita
5 days ago
C) The stakeholders have provided a specific deadline to meet.
upvoted 0 times
...
Elizabeth
12 days ago
B) The majority of the team can only meet on a weekly basis.
upvoted 0 times
...
Wendell
15 days ago
A) Each feature will have a different owner.
upvoted 0 times
...
...
Devorah
1 months ago
Emily
upvoted 0 times
...
Carolann
1 months ago
Hmm, I'm not sure. Is the answer 'all of the above'? Agile projects can be tough to manage with all those moving parts!
upvoted 0 times
...
Almeta
1 months ago
I'm going to go with B on this one. If the majority of the team can only meet weekly, that's going to make it challenging to coordinate the concurrent feature development.
upvoted 0 times
Hubert
21 days ago
User 2: Yeah, it could definitely impact the coordination of the features being developed.
upvoted 0 times
...
Rikki
27 days ago
User 1: I agree, if the team can only meet weekly, it might slow down progress.
upvoted 0 times
...
...
Dell
2 months ago
I agree with Tiara. C is the right answer here. Agile is all about being adaptable, and a fixed deadline from stakeholders could really throw a wrench in that.
upvoted 0 times
Ciara
27 days ago
D) Each feature has a specific budget allocation.
upvoted 0 times
...
Laquanda
27 days ago
C) The stakeholders have provided a specific deadline to meet.
upvoted 0 times
...
Lanie
29 days ago
B) The majority of the team can only meet on a weekly basis.
upvoted 0 times
...
Roselle
1 months ago
A) Each feature will have a different owner.
upvoted 0 times
...
...
Carrol
2 months ago
But what about option C? If the stakeholders have provided a specific deadline, that could also be a concern for the project manager.
upvoted 0 times
...
Niesha
2 months ago
I agree with Chandra, if the team can only meet weekly, it might slow down the development process.
upvoted 0 times
...
Chandra
2 months ago
I think the project manager should be concerned about option B.
upvoted 0 times
...
Tiara
2 months ago
I think the correct answer is C. The stakeholders providing a specific deadline is a concern for an agile project manager since it can limit the flexibility and iterative nature of the agile process.
upvoted 0 times
Kandis
27 days ago
D: Agreed, flexibility is key in agile project management.
upvoted 0 times
...
Marlon
1 months ago
C: Definitely, it can make it hard to prioritize and adjust as needed.
upvoted 0 times
...
Brandee
2 months ago
B: Yeah, it goes against the whole idea of adapting to change.
upvoted 0 times
...
Mitsue
2 months ago
A: I think it's C too. A strict deadline can be a challenge in agile.
upvoted 0 times
...
...

Save Cancel