Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 3 Question 28 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 28
Topic #: 3
[All PK0-005 Questions]

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Show Suggested Answer Hide Answer
Suggested Answer: A

A Finish-to-Start dependency implies that a subsequent activity cannot start until a previous one finishes. In this scenario, the manufacturing process (subsequent activity) cannot begin until the critical raw materials (previous activity) have been delivered. This type of dependency is the most common in project schedules and is likely being affected by the global shipping slowdown, causing delays in the start of the project's production run.


Contribute your Thoughts:

Page
2 months ago
That's a good point, Clay. It could be Start-to-start if the project can begin even with delayed deliveries.
upvoted 0 times
...
Clay
2 months ago
But what if the project can start even if the materials are not finished being delivered? Maybe it's Start-to-start.
upvoted 0 times
...
Leonor
2 months ago
I bet the project manager is having a meltdown over this delayed shipment. Finish-to-start all the way!
upvoted 0 times
...
Ilona
2 months ago
This is easy, it's Finish-to-start. The shipping slowdown is causing a domino effect on the whole production schedule.
upvoted 0 times
...
Tawna
2 months ago
I agree with Page, because the project can't start until the raw materials are finished being delivered.
upvoted 0 times
...
Evangelina
2 months ago
Hmm, I'm torn between Finish-to-start and Start-to-start, but I'll go with Finish-to-start since the question mentions the delay is from the beginning.
upvoted 0 times
...
Hobert
2 months ago
The correct answer is Finish-to-start. The late delivery of raw materials means the production can't even start on time.
upvoted 0 times
Annice
2 months ago
C: I agree, it's important to identify these dependencies early on to mitigate any potential risks.
upvoted 0 times
...
Tandra
2 months ago
B: Yeah, it's frustrating when external factors like shipping delays impact your project timeline.
upvoted 0 times
...
Jaime
2 months ago
A: That makes sense, the late delivery of raw materials is definitely causing a delay in production.
upvoted 0 times
...
...
Page
2 months ago
I think the most likely dependency is Finish-to-start.
upvoted 0 times
...
Amos
2 months ago
I think it's a Start-to-start dependency. The shipping slowdown is affecting the start of the production run.
upvoted 0 times
Teddy
1 months ago
D: That's a good idea, we need to be prepared for unexpected delays like this.
upvoted 0 times
...
Kristeen
1 months ago
C: Maybe we should look into alternative suppliers to avoid this issue in the future.
upvoted 0 times
...
Ashanti
2 months ago
B: I agree, it makes sense that the delay in shipping would impact the start of the project.
upvoted 0 times
...
Reid
2 months ago
A: I think it's a Start-to-start dependency. The shipping slowdown is affecting the start of the production run.
upvoted 0 times
...
...
Troy
3 months ago
It's definitely a Finish-to-start dependency. The late delivery of raw materials will delay the entire production run from the beginning.
upvoted 0 times
Merlyn
2 months ago
I agree, the late delivery of raw materials will definitely delay the production run from the beginning.
upvoted 0 times
...
Margart
2 months ago
A) Finish-to-start
upvoted 0 times
...
...

Save Cancel