Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 2 Question 43 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 43
Topic #: 2
[All PK0-005 Questions]

A project manager is monitoring the performance of the development team and creates the following view:

Planned Task Completion

Actual Task Completion

Which of the following describes the status of the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

Comprehensive and Detailed Step-by-Step

If the actual task completion is lagging behind the planned task completion, the project is behind schedule. This indicates that the project is not progressing as planned and may require corrective actions such as resource reallocation or schedule adjustments.


CompTIA Project+ PK0-005 Official Study Guide, Chapter 7: Monitoring Project Performance

Contribute your Thoughts:

Lanie
2 days ago
The actual task completion is lower than the planned, so I'd say B) Behind schedule is the correct answer.
upvoted 0 times
...
Tiera
8 days ago
I believe the project is on schedule, sometimes delays happen.
upvoted 0 times
...
Chana
13 days ago
I agree with Leonie, the actual task completion is less than planned.
upvoted 0 times
...
Leonie
16 days ago
I think the project is behind schedule.
upvoted 0 times
...

Save Cancel