Question #: 36
Topic #: 2
[All PK0-005 Questions]

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Show Suggested Answer Hide Answer
Suggested Answer: B

A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.


Contribute your Thoughts:

Margurite
3 days ago
I agree with Dalene. During the Sprint review, the team presents the status of each task.
upvoted 0 times
...
Dalene
7 days ago
I think the answer is B) Sprint review.