Question #: 36
Topic #: 2
[All PK0-005 Questions]

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?

Show Suggested Answer Hide Answer
Suggested Answer: B

A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.


Contribute your Thoughts:

Shawn
2 months ago
I'm gonna go with B) Sprint review. Anything else would just be a waste of time. Let's get to the good stuff!
upvoted 0 times
...
Rory
2 months ago
Hah, Daily Scrum? Are we still in the Stone Age? B) Sprint review is where the magic happens, my friends.
upvoted 0 times
...
Aliza
2 months ago
B) Sprint review, no doubt. Who needs a daily scrum when you can have a party and show off your work to the entire team?
upvoted 0 times
...
Elina
2 months ago
C'mon, it's gotta be B) Sprint review. That's the whole point of the exercise, right? Reviewing the backlog and keeping everyone in the loop.
upvoted 0 times
Vicky
26 days ago
Sprint review is the correct answer. It's all about reviewing the backlog and ensuring transparency within the team.
upvoted 0 times
...
Melinda
1 months ago
I agree, it's definitely B) Sprint review. It's important to keep everyone informed and on track.
upvoted 0 times
...
Loren
2 months ago
Yes, you're right. B) Sprint review is when the team presents the status of each task from the backlog.
upvoted 0 times
...
...
Chandra
2 months ago
Definitely B) Sprint review. We all know that's when the team showcases their work and gets feedback from stakeholders.
upvoted 0 times
Renea
1 months ago
It really helps us stay on track and ensure we're meeting the stakeholders' expectations.
upvoted 0 times
...
Yen
1 months ago
I always find the Sprint review to be a valuable part of the process.
upvoted 0 times
...
Reuben
1 months ago
It's also a good opportunity to gather feedback and make any necessary adjustments.
upvoted 0 times
...
Winifred
2 months ago
Yes, I agree. The Sprint review is where we demonstrate the completed work.
upvoted 0 times
...
...
Micaela
2 months ago
I think the correct answer is B) Sprint review. That's when the team discusses the progress and status of the tasks in the backlog.
upvoted 0 times
Kristofer
1 months ago
The Daily Scrum is a daily stand-up meeting to discuss what each team member is working on.
upvoted 0 times
...
Lavonda
1 months ago
I think the Sprint retrospective happens after the Sprint review to discuss what went well and what could be improved.
upvoted 0 times
...
Benton
1 months ago
It's important to review the backlog regularly to ensure progress is being made.
upvoted 0 times
...
Lonny
2 months ago
I agree, the Sprint review is when the team presents the status of each task.
upvoted 0 times
...
...
Margurite
3 months ago
I agree with Dalene. During the Sprint review, the team presents the status of each task.
upvoted 0 times
...
Dalene
3 months ago
I think the answer is B) Sprint review.
upvoted 0 times
...

Save Cancel