Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 10 Question 8 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 8
Topic #: 10
[All PK0-005 Questions]

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Show Suggested Answer Hide Answer
Suggested Answer: C

Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel