During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Show Suggested Answer Hide Answer
Suggested Answer: B

A RACI matrix clarifies roles and responsibilities for tasks, reducing confusion and disagreements among team members. Missing or incomplete information in the RACI matrix could lead to disputes, as it is a key tool for accountability in project management per CompTIA Project+.


Contribute your Thoughts:

Irma
3 days ago
I think the reason they are disagreeing is because some work packages are missing from the WBS.