BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-004 Topic 5 Question 24 Discussion

Actual exam question for CompTIA's PK0-004 exam
Question #: 24
Topic #: 5
[All PK0-004 Questions]

A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel