A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?
Currently there are no comments in this discussion, be the first to comment!