Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-004 Topic 2 Question 16 Discussion

Actual exam question for CompTIA's PK0-004 exam
Question #: 16
Topic #: 2
[All PK0-004 Questions]

A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines. Which of the following is an example of mitigation?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel