Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-004 Topic 1 Question 12 Discussion

Actual exam question for CompTIA's PK0-004 exam
Question #: 12
Topic #: 1
[All PK0-004 Questions]

A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete

the project on time. Many of these tasks were performed by the former project sponsor.

Which of the following types of change does this illustrate?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel