Tulip Rose Industries is using a restricted approach to tendering for a new contract for the facilities management of their seven factories which produce furniture made of organic materials. What is likely to be the reason they are using a restricted approach?
you would use a restricted approach when interest is likely to be high. The buyer needs a method of de-selecting unsuitable bidders and creating a shortlist of acceptable organisations.
For complex requirements you could use both an open or restrictive tender- the difference between the approaches is about how many bids you're likely to get rather than the complexity of it.
Lindy
5 months agoArmando
5 months agoLeonor
5 months agoPaola
4 months agoCristal
4 months agoIdella
4 months agoGeorgene
5 months agoKallie
4 months agoJohana
4 months agoRaylene
5 months agoLoreta
5 months agoLouvenia
5 months agoStephaine
5 months agoKenneth
6 months agoCherry
5 months agoShantell
5 months agoDorinda
6 months agoAlfred
6 months agoSantos
5 months agoChristiane
5 months agoKeena
6 months agoElfriede
6 months agoTamera
6 months ago