What is meant by Stakeholder Mapping? Describe a tool that can be used by a Procurement Professional to map the stakeholders at their organisation (25 points)
How to approach this question:
- Define stakeholder mapping -- completing an analysis of the stakeholders of an organisation and dividing them into categories depending on certain characteristics. This is often represented visually on a graph or matrix.
- Describe a Stakeholder mapping tool -- the most common tool is Mendelow's Stakeholder Matrix so I would recommend using this one. It is explained in detail in the study guide. However, the question is open so you could choose to describe another tool such as Edgar's Stakeholder Position Analysis if you so wished. You wouldn't be wrong choosing this, but honestly, I'd just go for Mendelow. You can't go wrong with Mendelow. Because the Matrix has 4 sections you can imagine you'd get 5 points for the definition of stakeholder mapping, and 5 points for each of the quadrants of the matrix.
Essay Plan:
Introduction - The reason why stakeholder mapping is important is because interests and expectations of stakeholder groups will be different and possibly conflicting. Mapping this allows an organisation to see the variety and decide on an appropriate management style for each stakeholder group.
Paragraph 1 - Mendelow's Power / Interest Matrix maps stakeholders based on their influencing power and the strength of their motivation to use that power. It uses a 2x2 grid and defines power as high or low and interest and high or low. It then provides four strategies for managing the stakeholders based on which quadrant of the grid the stakeholder falls into. These 4 categories are:
Paragraph 2 - Keep satisfied -- high power but low interest. If the stakeholder becomes dissatisfied or concerned their interest may peak. Examples include regulatory bodies, shareholders, senior management. The best approach is to keep them up to date so they are informed of what is going on, but do not burden them with information they do not need.
Paragraph 3 - Manage Closely -- AKA Key players -- includes major customers, key suppliers, partners, senior management. These stakeholders need to know everything that is going on and approve of what is going on. The recommended strategy is early involvement and participation, and integrating their goals with yours. This group requires regular communication and meetings. You should take their opinions on board.
Paragraph 4- Monitor -- minimum effort required -- this is the low priority group as they have low power and low interest. Includes small volume suppliers and other organisational functions with no direct interest in your activities. This group does not need to receive regular communication.
Paragraph 5 - Keep informed - high interest, but low power. If they're not kept in the loop and understand the need for decisions, they may lobby together to protect their interest if they feel threatened. Employee groups, suppliers and community groups may be in this category. This group should receive regular communication.
Conclusion - Mendelow created the matrix in 1991 and it is still used today. It is a popular management tool due to its simplicity. It's important to notes that stakeholders can move through the matrix- it isn't stagnant. For example, at the beginning of a project a manager in another department may be classed as 'low priority' because they are seen to have no interest and no power in the project. However, as the project progresses the manager may become interested. They will then transfer into the keep informed category. Therefore, the matrix should be redone regularly throughout the lifetime of a project to capture any movements. The matrix should also be redone for each individual project -- it cannot be assumed that a stakeholder who had interest in one project would be interested in another.
Tutor Notes
- The above essay plan is basically the entire essay, I got carried away. The only thing you'd need to add into that is an example of a stakeholder for each of the sections! (e.g. the CEO is high power, but low interest stakeholder for the procurement department. He/ She doesn't care about the day to day operations but should be kept informed of any big news). For your examples you could use your own place of work.
- At level 4 you don't have to analyse the model, you just have to be able to memorise it and repeat it. Mendelow comes up again at Level 5 and 6 in a bit more detail. If you want to score super bonus points you could mention in your conclusion that the main disadvantage of Mendelow's Matrix is that it doesn't take into consideration the stakeholder's position on the project -- whether they're for it or against it. Therefore, it doesn't provide the full picture or provide much help on how to manage stakeholders. E.g. two stakeholders might both be in 'manage closely' section, but one is for the project and the other against -- they'd need to be handled very differently!
- Study guide p. 65