UVW is preparing its manufacturing account for the year ended 30 June 20X7 The following information is available:

What is UVWs prime cost for year ended 30 June 20X7?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Alverta
25 days ago
I'm definitely going with B) $344,000. It's the only answer that matches the raw material and direct labor costs given in the information. Whoever wrote this question must have been trying to trick us!
upvoted 0 times
...
Merri
26 days ago
I almost went with B, but then I remembered that prime cost includes indirect labor too. So I'm going to have to say D) $397,000 is the right answer. Gotta love these trick questions!
upvoted 0 times
Marsha
8 days ago
It's always important to carefully consider all the elements that make up prime cost. D) $397,000 definitely seems like the most accurate option here.
upvoted 0 times
...
Gilberto
11 days ago
I was also leaning towards B at first, but after considering all the components of prime cost, I think D) $397,000 is the right choice.
upvoted 0 times
...
Isadora
12 days ago
I agree with you, prime cost includes direct materials and direct labor, as well as indirect labor. So D) $397,000 seems like the correct answer.
upvoted 0 times
...
...
Dorinda
1 months ago
Hmm, I see your point. Let's double check our calculations before the exam.
upvoted 0 times
...
Tatum
1 months ago
Hmm, this one's tricky. I'm going to go with C) $389,000, but I'm not totally sure. Maybe I should have paid more attention in class.
upvoted 0 times
Herminia
9 days ago
User3: I agree with User1, B) $344,000 seems right.
upvoted 0 times
...
Jeanice
16 days ago
I'm leaning towards A) $352,000.
upvoted 0 times
...
Melinda
25 days ago
I think it's B) $344,000.
upvoted 0 times
...
...
Skye
1 months ago
D) $397,000 looks like the correct answer to me. The question asks for the prime cost, which includes raw material and direct labor, and the total of those two figures is $397,000.
upvoted 0 times
Tawna
7 days ago
D) $397,000 is the correct prime cost for UVW.
upvoted 0 times
...
Roxanne
11 days ago
C) $389,000 is not the prime cost for UVW.
upvoted 0 times
...
Curt
15 days ago
B) $344,000 is also lower than the correct answer.
upvoted 0 times
...
Zana
27 days ago
A) $352,000 is too low for the prime cost.
upvoted 0 times
...
...
Linette
1 months ago
I calculated it differently, I believe it is $344,000.
upvoted 0 times
...
Josephine
2 months ago
I think the answer is B) $344,000. The total raw material cost is $289,000, and the total direct labor cost is $55,000, which adds up to $344,000.
upvoted 0 times
Catalina
18 days ago
I'm not sure, but I think we need to consider all direct costs to calculate the prime cost accurately.
upvoted 0 times
...
Leonora
24 days ago
Actually, I believe the answer is D) $397,000 because the prime cost includes all direct costs related to production.
upvoted 0 times
...
Lashaunda
1 months ago
I think the answer might be C) $389,000 because we also need to consider the factory overhead costs.
upvoted 0 times
...
Lawrence
1 months ago
I agree with you, the prime cost is calculated by adding raw material cost and direct labor cost.
upvoted 0 times
...
...
Dorinda
2 months ago
I think the prime cost is $352,000.
upvoted 0 times
...