Certinia Exam PSA-Sysadmin Topic 4 Question 37 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 37
Topic #: 4
[All PSA-Sysadmin Questions]

Your company hired its first part-time employee that needs to be set up as a Consultant in PS

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Vilma
3 months ago
This is a tricky one, but I'd go with the 'Work Calendar' option. Seems like the most straightforward way to get the part-time utilization right.
upvoted 0 times
Jamie
2 months ago
True, but I still think the 'Work Calendar' option is the most straightforward choice.
upvoted 0 times
...
Rosendo
2 months ago
Creating a new 'Utilization Calculation' labeled Part Time could also work to ensure accuracy.
upvoted 0 times
...
Helene
2 months ago
I agree, but I think setting up a new 'Work Calendar' for 20 hours might be more accurate.
upvoted 0 times
...
Johana
3 months ago
I think creating a new 'Role' for Part Time Consultant would be the best option.
upvoted 0 times
...
...
Anisha
4 months ago
Wait, are we sure this consultant isn't just moonlighting as a superhero? Maybe they need a 'Cape and Mask' role too!
upvoted 0 times
...
Mabel
4 months ago
The 'Work Calendar' option sounds good to me. That way, you can set their schedule to 20 hours and the system will know how to track their time.
upvoted 0 times
Lavonna
2 months ago
The 'Work Calendar' option sounds good to me. That way, you can set their schedule to 20 hours and the system will know how to track their time.
upvoted 0 times
...
Paz
3 months ago
B) Create a new Part Time 'Work Calendar' for 20 hours
upvoted 0 times
...
Tasia
3 months ago
A) Create a new 'Role' indicating the user is a Part Time Consultant
upvoted 0 times
...
...
Marion
4 months ago
I think creating a new 'Utilization Calculation' labeled Part Time would also be important for accurate calculations.
upvoted 0 times
...
Royal
4 months ago
I agree with Layla, creating a new 'Role' will help in calculating utilization correctly.
upvoted 0 times
...
Kanisha
4 months ago
I bet the HR team is going to love this - 'Part Time Consultant' sounds like a fancy title for someone just working a few hours a week.
upvoted 0 times
Aron
3 months ago
I know, right? It's all about the title!
upvoted 0 times
...
Kiley
3 months ago
C) Create a new 'Utilization Calculation' labeled Part Time
upvoted 0 times
...
Helaine
3 months ago
B) Create a new Part Time 'Work Calendar' for 20 hours
upvoted 0 times
...
Yuriko
4 months ago
A) Create a new 'Role' indicating the user is a Part Time Consultant
upvoted 0 times
...
...
Layla
4 months ago
I think we should create a new 'Role' for the part-time consultant.
upvoted 0 times
...