Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Certinia Exam PSA-Sysadmin Topic 1 Question 36 Discussion

Actual exam question for Certinia's PSA-Sysadmin exam
Question #: 36
Topic #: 1
[All PSA-Sysadmin Questions]

A manager was looking at utilization for a resource for the last two months. The resource was identified as 80% utilized for each month, but the subtotal section showed 160% for the user for that same two month period.

How can the report be fixed to show 80% instead of 160%?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Lorita
3 days ago
I'm not sure about that, maybe creating a Summary Level formula could also work to correct the subtotal calculation.
upvoted 0 times
...
Arlyne
4 days ago
This question is really tricky! I think the key is to understand how the utilization calculation is being done. The report seems to be double-counting the resource's time.
upvoted 0 times
...
Salley
5 days ago
I agree with Tanja, that seems like the most logical solution to fix the report.
upvoted 0 times
...
Tanja
12 days ago
I think we should adjust the resource's work calendar to 40 hours and refresh the report.
upvoted 0 times
...

Save Cancel