BCS Exam TM12 Topic 6 Question 52 Discussion

Actual exam question for BCS's TM12 exam
Question #: 52
Topic #: 6
[All TM12 Questions]

An agile development team decides to hire a tester who has always worked:

- in independent test teams, reporting the problems found in a defect tracking system

- in safety-critical projects, with a stronger focus on the quality of the product than on time and budget.

This agile team is focused on short-term goals to get the product released on time and within budget.

Which of the following answers would you expect to be most likely true in this scenario?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: D