BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam TM12 Topic 5 Question 27 Discussion

Actual exam question for BCS's TM12 exam
Question #: 27
Topic #: 5
[All TM12 Questions]

Assume you are managing the system testing phase of a project.

The system test execution period is scheduled to twenty weeks.

All tests are manual tests. You are following a risk-driven test approach.

During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.

Which of the following would you expect to be the best way to respond to this situation?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel