A company produces kitchens to order. Customers specify the design of the kitchen by using a computer-aided design tool, provided on the company's website. The tool allows customers to select products, such as cabinets and cookers, and place them into a floor plan of the kitchen that they have specified.
Once the customer confirms the design, an order is placed and the customer is given a planned installation date for the kitchen. The company orders the raw materials for the kitchen and the kitchen is built by its skilled carpenters The customer can track the progress of the build on the Internet. If the kitchen Is likely to be delivered later than originally promised, a control action is taken to bring it back on schedule
A Business Activity Model (BAM) developed for the company has 'sell bespoke kitchens' as its doing activity.
Which of the following activities would be directly linked by a logical dependency arrow to or from this doing activity?