Bluesky Travel is an independent travel agency specialising in luxury bespoke holidays, which is introducing a new booking process. So far, the following key changes have been made:

1) The new Commercial Off The Shelf (COTS) software package for making bookings has been installed and is working

2) Data is being migrated from the old computer system to the COTS software package

3) The IT department has documented the configuration of the COTS system

4) The legal department has confirmed that the new COTS system is compliant with company policies.

In taking a holistic approach, which of the following areas of the POPII Model have NOT yet been addressed by the changes identified?

Show Suggested Answer Hide Answer
Suggested Answer: D

The POPII Model consists of four areas: Organisation and Process, Process and People, People and Technology, and Organisation and Information. Based on the changes identified, it appears that the Organisation and Information area have NOT yet been addressed. This area deals with the organisation's data assets, such as policies, procedures, and information resources, and how this information is used and shared.