All stories in your project are linked to epics within the same project. Using a bulk operation, you moved some stories to another project. What happens to the epics?
Epics are moved automatically but epic links are lost when stories are moved to another project using a bulk operation. This is because epics are a type of issue, and issues can be moved across projects. However, epic links are a type of issue link, and issue links cannot be moved across projects. Therefore, the stories will lose their epic links after the move, and the epics will remain in the original project.Reference:[Moving multiple issues], [Managing Jira Projects Data Center and Server: Certification Bundle]