A Scrum project has the following five configured versions:
How many of them will be available in the versions panel of the project backlog?
Three versions will be available in the versions panel of the project backlog: epsilon, delta, and gamma. These are the three unreleased versions in the project, as shown in the image. The versions panel only shows unreleased versions, as they are used to plan and track the progress of upcoming releases. Released and archived versions are not shown in the versions panel, as they are considered completed and no longer relevant for planning purposes.Reference:[Working with versions], [Managing Jira Projects Data Center and Server: Certification Bundle]