Atlassian Exam ACP-100 Topic 9 Question 89 Discussion

Actual exam question for Atlassian's ACP-100 exam
Question #: 89
Topic #: 9
[All ACP-100 Questions]

The operations team currently uses the OPS project to track their tasks. They have a new requirement to begin handling change requests. Inspect the partial summary of the current OPS project configuration:

Which two requirements would require creating a new project? (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: D, E

Contribute your Thoughts:

Hannah
5 months ago
Hmm, I'm leaning towards B and E. The due date field is a dead giveaway, and the different component leads seem like a no-brainer. Let's see what the rest of the class thinks!
upvoted 0 times
...
Leslee
5 months ago
Ah, I see. The key is that the change requests need to be in a separate project. I'd go with B and C, those seem like the obvious choices.
upvoted 0 times
Camellia
3 months ago
Definitely, those requirements would justify a separate project for change requests.
upvoted 0 times
...
Lashanda
3 months ago
I agree, B and C make the most sense for creating a new project.
upvoted 0 times
...
...
Vernell
5 months ago
I'm not sure about this one. I'll have to think it through carefully. Maybe C and D, since the notifications and workflow would be different?
upvoted 0 times
Dominic
4 months ago
Yes, I agree. Those are the two requirements that would require creating a new project.
upvoted 0 times
...
Veronika
4 months ago
I think you're right. The workflow and notifications would definitely be different for change requests.
upvoted 0 times
...
...
Rosalyn
5 months ago
I agree with you, Louvenia. Option C and D seem to involve significant changes that may need a separate project.
upvoted 0 times
...
Louvenia
5 months ago
I think option C and D would require creating a new project.
upvoted 0 times
...
Winfred
5 months ago
Hmm, this looks tricky. I think the answer might be B and C, since change requests would need different components and workflows compared to the current OPS project.
upvoted 0 times
Wade
4 months ago
User 2
upvoted 0 times
...
Tom
4 months ago
User 1
upvoted 0 times
...
Nobuko
4 months ago
User 2
upvoted 0 times
...
Christiane
5 months ago
Agreed, those requirements would definitely require creating a new project.
upvoted 0 times
...
Ayesha
5 months ago
User 1
upvoted 0 times
...
Keena
5 months ago
Yeah, change requests needing different component leads and workflows makes sense.
upvoted 0 times
...
Deangelo
5 months ago
I think the answer is B and C too.
upvoted 0 times
...
...

Save Cancel