Question #: 60
Topic #: 2
[All ACP-100 Questions]

An issue is showing the Time Tracking section as follows:

There is clearly an hour's difference between the Original and Remaining estimates.

Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Julianna
6 hours ago
A and B seem like the most likely reasons. Time tracking needs to be enabled to log time, and adjusting the remaining estimate without logging effort would definitely result in Logged Time showing as Not Specified.
upvoted 0 times
...
Kendra
7 hours ago
I agree with Chana. Another possible reason could be that the remaining estimate was adjusted without logging any effort.
upvoted 0 times
...
Chana
4 days ago
I think the reason Logged Time is showing as Not Specified could be because time tracking was not enabled when the work was logged.
upvoted 0 times
...