Question #: 10
Topic #: 6
[All Better-Business-Cases-Practitioner Questions]

Which statement should be recorded under the Programme and Project Management heading?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Herman
2 months ago
I agree with Amber, option A focuses on the core purpose of Programme and Project Management.
upvoted 0 times
...
Amber
2 months ago
But option A talks about planning transformation, which is crucial for Programme and Project Management.
upvoted 0 times
...
Caprice
3 months ago
This exam is as clear as mud! I'm going to go with option B and hope for the best.
upvoted 0 times
Talia
2 months ago
I agree, let's go with option B and see how it goes.
upvoted 0 times
...
Heidy
2 months ago
I think option B is a good choice.
upvoted 0 times
...
...
Tamekia
3 months ago
C mentions a financial advisor, which is probably more of an administrative task. Not really a project management item in my opinion.
upvoted 0 times
Arlene
2 months ago
D) Plans could meet with substantial opposition from parents and staff.
upvoted 0 times
...
Kati
2 months ago
C) A financial special advisor has been appointed from Western Area Finance, an auditing organization.
upvoted 0 times
...
Theresia
2 months ago
A) The Consortium has been formed to plan the transformation of education and learning for 11 to 18 year olds throughout the Western Area.
upvoted 0 times
...
...
Mickie
3 months ago
I disagree, I believe option D is more relevant.
upvoted 0 times
...
Lamar
3 months ago
A talks about the overall transformation, which seems more like a programme-level objective. I'd go with that one.
upvoted 0 times
...
Christiane
3 months ago
D seems more relevant to me. Anticipating opposition is an important part of project planning.
upvoted 0 times
Virgie
2 months ago
D) Plans could meet with substantial opposition from parents and staff.
upvoted 0 times
...
Johana
2 months ago
C) A financial special advisor has been appointed from Western Area Finance, an auditing organization.
upvoted 0 times
...
Cammy
2 months ago
B) The redefinition of jobs is to be negotiated with teaching unions and communicated to all staff.
upvoted 0 times
...
Domonique
2 months ago
A) The Consortium has been formed to plan the transformation of education and learning for 11 to 18 year olds throughout the Western Area.
upvoted 0 times
...
...
Amber
3 months ago
I think option A should be recorded.
upvoted 0 times
...
Nobuko
3 months ago
I think B is the correct answer. The redefinition of jobs is definitely a project management issue.
upvoted 0 times
Candida
2 months ago
C) A financial special advisor has been appointed from Western Area Finance, an auditing organization.
upvoted 0 times
...
Billy
2 months ago
B) The redefinition of jobs is to be negotiated with teaching unions and communicated to all staff.
upvoted 0 times
...
Gretchen
2 months ago
B) The redefinition of jobs is to be negotiated with teaching unions and communicated to all staff.
upvoted 0 times
...
Ronna
2 months ago
A) The Consortium has been formed to plan the transformation of education and learning for 11 to 18 year olds throughout the Western Area.
upvoted 0 times
...
Irma
3 months ago
A) The Consortium has been formed to plan the transformation of education and learning for 11 to 18 year olds throughout the Western Area.
upvoted 0 times
...
...

Save Cancel