Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

APMG-International Exam Better-Business-Cases-Practitioner Topic 4 Question 2 Discussion

Actual exam question for APMG-International's Better Business Cases Practitioner exam
Question #: 2
Topic #: 4
[All Better Business Cases Practitioner Questions]

Using the Scenario, answer the following questions about the Management Case section of the Full Business Case for

the Pittville project.

Decide whether the entry is appropriate for the document identified and select the responses that support your decision.

Remember to select 2 answers to each question.

The Programme and Project Management Framework section states:

1. The Programme Director is to be responsible for the Western Area Learning Improvements Programme.

2. Project progress reports are to be provided to the Consortium at the end of each month.

Which 2 statements apply to these entries?

Show Suggested Answer Hide Answer
Suggested Answer: A, E

Contribute your Thoughts:

Gabriele
3 months ago
I think we should remove entry 2 and document project reporting in the Project Plan.
upvoted 0 times
...
Jamika
3 months ago
I believe no change is needed for entry 1. It seems appropriate to me.
upvoted 0 times
...
Ahmed
3 months ago
I agree with Shasta. The Programme Director shouldn't be solely responsible.
upvoted 0 times
...
Shasta
3 months ago
I think we should amend entry 1 because the Consortium should be jointly accountable.
upvoted 0 times
...
Glory
3 months ago
No changes to entry 2 make sense. The project framework should include reporting arrangements in relation to the programme. It's all about that sweet, sweet communication, am I right?
upvoted 0 times
Veronika
3 months ago
Absolutely, communication is key in any project. It's important to have clear reporting structures in place.
upvoted 0 times
...
Graciela
3 months ago
No change to entry 2, because the project framework should include project reporting arrangements in relation to the programme.
upvoted 0 times
...
...
Otis
3 months ago
Haha, entry 2 should definitely be removed. Project reporting arrangements belong in the Project Plan, not the Programme Framework. Someone's been watching too many episodes of 'The Office'!
upvoted 0 times
...
Antonette
4 months ago
I agree with amending entry 1. The Senior Responsible Owner should not be the Programme Director, that's not appropriate. C'mon, that's just basic governance!
upvoted 0 times
Gertude
3 months ago
B) Amend entry 1, because the Senior Responsible Owner should NOT be the Programme Director.
upvoted 0 times
...
Breana
3 months ago
A) Amend entry 1, because the Western Area Learning Consortium should be jointly accountable for the Programme.
upvoted 0 times
...
...
Kelvin
4 months ago
I think entry 1 should be amended because the Western Area Learning Consortium should be jointly accountable for the Programme. The Programme Director shouldn't be solely responsible.
upvoted 0 times
Josue
3 months ago
I agree, the Consortium should share responsibility for the Programme.
upvoted 0 times
...
Cristen
3 months ago
B) Amend entry 1, because the Senior Responsible Owner should NOT be the Programme Director.
upvoted 0 times
...
Earleen
3 months ago
A) Amend entry 1, because the Western Area Learning Consortium should be jointly accountable for the Programme.
upvoted 0 times
...
...

Save Cancel