Answer the following questions about the use of the Agile principles.

Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional

wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.

Which Agile principle MOST influences this course of action?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Lou
3 months ago
That's a good point, Edna. Maybe both B) and C) principles are relevant in this scenario.
upvoted 0 times
...
Edna
3 months ago
But isn't C) Build incrementally from firm foundations also important in this situation? Maybe we should have caught the issues earlier in the process.
upvoted 0 times
...
Geraldine
3 months ago
D) Communicate continuously and clearly. This whole situation could have been avoided if the team was on the same page from the start. Gotta keep those lines of communication open!
upvoted 0 times
Stevie
2 months ago
B) Never compromise quality.
upvoted 0 times
...
Hester
3 months ago
A) Collaborate.
upvoted 0 times
...
...
Cherilyn
3 months ago
I agree with Lou, if the items do not meet the required standards, quality should not be compromised.
upvoted 0 times
...
Lou
3 months ago
I think the answer is B) Never compromise quality.
upvoted 0 times
...
Ronnie
4 months ago
Haha, I bet the contractor tried to use some cheap shag carpet and neon paint. Back to the drawing board! B) Never compromise quality is the way to go.
upvoted 0 times
Lizette
3 months ago
Exactly! Quality should always be a top priority.
upvoted 0 times
...
Lizette
3 months ago
B) Never compromise quality.
upvoted 0 times
...
...
Dorian
4 months ago
I'd say C) Build incrementally from firm foundations. The key is to establish a solid base and then build upon it, even if that means reworking some things along the way.
upvoted 0 times
...
Dortha
4 months ago
Definitely B) Never compromise quality. Agile is all about delivering working software, and that includes meeting the required standards. No way we're cutting corners here!
upvoted 0 times
Denae
3 months ago
C) Build incrementally from firm foundations.
upvoted 0 times
...
Jacinta
3 months ago
B) Never compromise quality.
upvoted 0 times
...
Shasta
4 months ago
A) Collaborate.
upvoted 0 times
...
...