Question #: 3
Topic #: 3
[All APM-PMQ Questions]

Which of the activities below would provide final assurance of a project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Product testing ensures the deliverables meet the intended specifications and are ready for deployment, which is the final assurance step before project closure.


Contribute your Thoughts:

Tasia
1 days ago
Testing the product is definitely the way to go. You can't have final assurance without thoroughly checking the product, right?
upvoted 0 times
...
Mary
2 days ago
I think testing of a product would provide final assurance.
upvoted 0 times
...
Regenia
14 days ago
I think option C is the correct answer. Testing the product is crucial to ensure it meets the requirements and functions as expected.
upvoted 0 times
Gerry
4 days ago
I agree, testing the product is essential to ensure its quality.
upvoted 0 times
...
...