Question #: 8
Topic #: 2
[All APM-PMQ Questions]

You are the project manager of a project that's currently in the definition phase. After your first meeting, the project sponsor has asked to see the integrated project management plan.

In this scenario, which of the following best describes the importance of an integrated project management plan?

Show Suggested Answer Hide Answer
Suggested Answer: D

An integrated project management plan ensures alignment between the project manager and sponsor by setting clear expectations and outlining the project's scope, schedule, and deliverables.


Contribute your Thoughts:

Larae
4 days ago
As a project manager, I can't imagine going into a project without a solid integrated plan. Option D is the clear winner here.
upvoted 0 times
...
Winfred
13 days ago
Option D is definitely the best choice. The integrated plan helps align the project manager and sponsor's understanding of the project's goals and deliverables.
upvoted 0 times
...
Casie
14 days ago
I believe it also helps new team members understand the project better.
upvoted 0 times
...
Mickie
15 days ago
I agree with Marjory. It also provides a baseline for measuring success.
upvoted 0 times
...
Kandis
18 days ago
The integrated project management plan is crucial for setting expectations between the project manager and sponsor. Option D is the way to go.
upvoted 0 times
Paola
4 days ago
B) It provides a baseline to measure the project's success before the project is closed.
upvoted 0 times
...
Margurite
7 days ago
A) It helps new team members understand the project during their onboarding.
upvoted 0 times
...
...
Marjory
19 days ago
I think the integrated project management plan is important for setting expectations with the sponsor.
upvoted 0 times
...

Save Cancel