The question: 'Is the project actually following the processes and procedures as set out in the quality plan?' would be answered by?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Helga
3 days ago
Quality assurance, of course! It's like the project manager's personal quality police - making sure everything is up to snuff.
upvoted 0 times
...
Albina
4 days ago
D) Quality improvement. Gotta keep those processes and procedures sharp, am I right? Continuous improvement is key!
upvoted 0 times
...
Janella
5 days ago
A) Quality alignment. That's the one where we make sure the project is in sync with the quality plan, isn't it?
upvoted 0 times
...
Cassi
7 days ago
B) Quality control. It's all about monitoring and adjusting the actual performance to meet the requirements.
upvoted 0 times
...
Olive
10 days ago
C) Quality assurance. That's the one that checks if the project is following the established processes and procedures, right?
upvoted 0 times
...
Yoko
1 months ago
I'm not sure, but I think it could also be B) Quality control to ensure compliance.
upvoted 0 times
...
Howard
1 months ago
I agree with Daren, quality assurance ensures the project follows the set processes.
upvoted 0 times
...
Daren
1 months ago
I think the answer is C) Quality assurance.