What are two characteristics of a Group in Workfront? (Choose two.)
Groups in Adobe Workfront serve as organizational entities that can be associated with specific Companies or Projects to manage workflows or permissions more effectively. Additionally, each Group can have a Group Administrator assigned, who is responsible for managing the group's settings, permissions, and workflows. These roles and associations help in structuring how work and permissions are allocated across different teams or departments.
What is unique to a Scrum iteration?
A Burndown Chart is a visual representation of work remaining versus time in a Scrum iteration. It is unique to agile methodologies like Scrum and is used to track the team's progress during a sprint. The chart helps teams visualize how much work is left to complete the sprint goal, making it a critical tool in Scrum.
Which group of project elements can be used to monitor an active project's progress?
The best combination of elements to monitor an active project's progress in Adobe Workfront is Gantt chart, project Condition, and Metrics. The Gantt chart provides a visual timeline of task dependencies and durations, the Condition field shows the project's current health (On Target, At Risk, etc.), and Metrics offer quantitative data to measure progress. Together, these provide a comprehensive view of a project's performance.
Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.
Marguerita
3 days agoCecil
7 days agoCassi
11 days agoEdison
21 days agoKris
25 days agoAaron
1 months agoJacob
1 months agoDacia
1 months agoAlecia
2 months agoGwenn
2 months agoMargret
2 months agoJohna
2 months agoLuann
3 months agoTyisha
3 months agoChantell
3 months agoLavina
3 months agoBok
3 months ago