Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD5-E809 Topic 4 Question 47 Discussion

Actual exam question for Adobe's AD5-E809 exam
Question #: 47
Topic #: 4
[All AD5-E809 Questions]

The optimization team is planning their next 3-month experimentation roadmap for the homepage. They have the following candidates:

A - 8 weeks to build, another estimated A weeks to complete (run), and a projected 20% lift in conversion rate. B - 5 weeks to build, another estimated 7 weeks to complete (run), and a projected 25% lift in conversion rate. C - 5 weeks to build another estimated 3 weeks to complete (run), and a projected 15% lift in conversion rate. D - Requires no development team resource, an estimated 7 weeks to complete (run), and a projected 10% lift in conversion rate.

Providing all the estimations are correct and the development team can only build one test at a time, how should they plan their roadmap?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel