Adobe Exam AD0-E908 Topic 2 Question 22 Discussion

Actual exam question for Adobe's AD0-E908 exam
Question #: 22
Topic #: 2
[All AD0-E908 Questions]

Refer to the exhibit.

Tyson has a capacity of 7 hours per day.

What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)

Show Suggested Answer Hide Answer
Suggested Answer: A, C

To ensure Tyson is not over-allocated in the Workload Balancer, a system administrator can take the following actions:

Edit Task Allocation: The administrator can adjust the allocation of hours for the 'Verify Intake Form' task. Specifically, they can redistribute the hours from Wednesday (where Tyson is over-allocated with 9 hours) to other days where Tyson has available capacity.

Reassign Task: The administrator can reassign the 'Kickoff Meeting' task to another user who has available capacity. This will immediately reduce Tyson's workload and ensure the task is still completed without overburdening Tyson.

Reference

Workfront documentation on using the Workload Balancer highlights these options for managing user allocations and ensuring workloads are balanced across team members.