Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 3 Question 16 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 16
Topic #: 3
[All AD0-E903 Questions]

Which project elements can be used to measure a project's adherence to its original schedule?

Show Suggested Answer Hide Answer
Suggested Answer: B

To measure a project's adherence to its original schedule, the most critical elements are Project Baselines, Planned Completion Dates, and Actual Completion Dates. The baseline captures the original planned schedule, while the planned and actual completion dates provide the data to compare the project's progress against the initial schedule. This comparison helps project managers identify any deviations from the original plan and assess the project's performance.


Contribute your Thoughts:

Sunny
11 days ago
I'm not sure about the answer. I think it could also be A) Number of tasks, actual completion dates, and project status. Those elements can also indicate adherence to the original schedule.
upvoted 0 times
...
Gwen
13 days ago
I agree with Santos. Project baselines help track the original schedule, and comparing planned vs actual completion dates gives a clear picture of adherence.
upvoted 0 times
...
Santos
16 days ago
I think the answer is B) Project baselines, planned completion dates, and actual completion dates.
upvoted 0 times
...
Shawnna
21 days ago
Option B seems to be the most comprehensive - project baselines, planned completion dates, and actual completion dates are key metrics to measure schedule adherence.
upvoted 0 times
Mariann
5 days ago
Yes, planned and actual completion dates help to see if we are on schedule.
upvoted 0 times
...
Anastacia
9 days ago
I agree, project baselines are important to track progress.
upvoted 0 times
...
...

Save Cancel