A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to 'Calculated Work' allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.
Chauncey
13 days agoJerrod
18 days agoFatima
23 days agoArminda
28 days agoTawna
1 month agoAnnelle
1 month agoCorinne
1 month agoLeanora
2 months agoAlida
2 months agoOdette
2 months agoErinn
2 months agoGlendora
2 months agoDonte
3 months agoPeter
3 months agoTom
3 months agoAmmie
3 months agoFrancesco
4 months agoBobbie
4 months agoAshleigh
2 months ago