Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 2 Question 4 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 4
Topic #: 2
[All AD0-E903 Questions]

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

Show Suggested Answer Hide Answer
Suggested Answer: B

In this scenario, the fact that Task 2's start date did not shift automatically despite its dependency on Task 1 suggests that a manual override was applied, resulting in a Task Constraint of 'Must Start On.' This type of constraint locks a task to a specific date, preventing it from dynamically adjusting based on changes to its predecessor. The other options either do not explain why the start date remained static or involve user-specific scheduling conflicts, which would not affect the system-driven date adjustment.


Contribute your Thoughts:

Lindsey
1 day ago
I think it’s definitely a manual change by the project owner.
upvoted 0 times
...
Abraham
7 days ago
Sounds like a Must Start On constraint issue.
upvoted 0 times
...
Willodean
13 days ago
I’m leaning towards option D, but it seems counterintuitive that changing to As Soon As Possible would make the date static. I need to double-check how constraints work in these scenarios.
upvoted 0 times
...
Hyman
18 days ago
I think option C could be a factor too. If the assignee has time off, it might prevent the task from shifting, but I’m not confident if that alone would keep the start date unchanged.
upvoted 0 times
...
Filiberto
24 days ago
I feel like I've seen a question similar to this before. Option B sounds plausible since manual changes can definitely impact the task constraints, but I wonder if it would really keep the date static.
upvoted 0 times
...
Billye
30 days ago
I remember studying how constraints can affect task scheduling. I think option A makes sense if a Commit Date was set, but I'm not entirely sure if it would override the predecessor relationship.
upvoted 0 times
...
Tawna
30 days ago
This seems straightforward to me. The question is clearly pointing to a constraint or manual change that prevented the planned start date from shifting. I'll review the options and choose the one that best fits the information provided.
upvoted 0 times
...
Silvana
1 month ago
Okay, I think I've got this. Based on the details, it sounds like the project owner or primary assignee may have manually changed the constraints or start date for Task 2, which would explain why it didn't shift as expected. I'll select the most likely option.
upvoted 0 times
...
Elbert
1 month ago
I'm a bit confused by this question. It seems like there could be a few different reasons why the planned start date of Task 2 didn't shift as expected. I'll need to carefully consider the details provided.
upvoted 0 times
...
Mona
1 month ago
Hmm, this is an interesting one. I think the key is understanding how the project constraints and scheduling work in this scenario. I'll need to review the options carefully and think through the potential causes.
upvoted 0 times
...
Bobbie
1 year ago
That's a good point, Leonardo. It could be a manual change by the project owner that caused the issue.
upvoted 0 times
...
Leonardo
1 year ago
I disagree, I believe it's because of option B. The project owner must have manually changed the start date.
upvoted 0 times
...
Dominga
1 year ago
Haha, what if the primary assignee had scheduled a vacation during the new planned start date for Task 2? That would be a classic case of bad timing, just like option C describes.
upvoted 0 times
...
Melissia
1 year ago
Hmm, I think the primary assignee must have submitted a Commit Date for the previous planned start date on Task 2, even though the project owner didn't accept it. That's likely the reason, as stated in option A.
upvoted 0 times
...
Chanel
1 year ago
The planned start date of Task 2 remained the same because the project owner manually changed the Task Constraint to Must Start On, as mentioned in option B.
upvoted 0 times
Glen
1 year ago
Yeah, that could have also played a role in keeping the planned start date the same.
upvoted 0 times
...
Halina
1 year ago
Maybe the primary assignee had already submitted a Commit Date for the previous planned start date on Task 2.
upvoted 0 times
...
Felix
1 year ago
That makes sense, it would explain why the planned start date didn't shift.
upvoted 0 times
...
Celia
1 year ago
I agree, it's important to be aware of how manual changes can impact the project schedule.
upvoted 0 times
...
Son
1 year ago
That makes sense, the manual change to the Task Constraint would definitely keep the planned start date static.
upvoted 0 times
...
Mira
1 year ago
I think the project owner manually changed the Task Constraint of Task 2 to Must Start On.
upvoted 0 times
...
...
Bobbie
1 year ago
I think the planned start date of Task 2 remained the same because of option A.
upvoted 0 times
...

Save Cancel