Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?
The Projected Date in Adobe Workfront is dynamically calculated based on the progress of the task, any task constraints, and its dependencies. This date provides a more accurate reflection of when a task is likely to be completed, considering the current progress and any updates to predecessor tasks. On the other hand, the Planned Date refers to the originally scheduled completion date, and the Estimated Date is not manually entered but inferred from system calculations.
Cammy
1 months agoDeja
2 days agoJosephine
9 days agoEdelmira
10 days agoMinna
1 months agoRobt
1 months agoRebbecca
1 days agoJenelle
19 days agoJacqueline
1 months agoWillie
19 days agoWilda
20 days agoEarnestine
1 months agoCassi
2 months agoEarnestine
14 days agoArthur
17 days agoReita
18 days agoKenneth
1 months agoGianna
2 months agoMinna
2 months ago