BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E903 Topic 1 Question 9 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 9
Topic #: 1
[All AD0-E903 Questions]

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.


Contribute your Thoughts:

Sena
1 months ago
I prefer the Must Start On constraint. It ensures that the tasks start exactly when we need them to.
upvoted 0 times
...
Veronika
1 months ago
Whichever option you choose, I just hope there's no 'last minute' pizza involved. I've had enough of that in my life, thank you very much!
upvoted 0 times
Lynelle
3 days ago
C) As Late As Possible
upvoted 0 times
...
Chaya
5 days ago
B) Must Start On
upvoted 0 times
...
Melina
6 days ago
I agree, last minute pizza is never a good idea.
upvoted 0 times
...
Ashton
8 days ago
C) As Late As Possible
upvoted 0 times
...
Yun
10 days ago
B) Must Start On
upvoted 0 times
...
Gearldine
18 days ago
A) Start No Later Than
upvoted 0 times
...
Michal
27 days ago
A) Start No Later Than
upvoted 0 times
...
...
Valene
1 months ago
I agree with Mila. It gives us flexibility to start the tasks earlier if needed.
upvoted 0 times
...
Mila
2 months ago
I think we should use the Start No Later Than constraint.
upvoted 0 times
...
Hoa
2 months ago
Hmm, I'm going with A) Start No Later Than. Gives a bit of a buffer, you know? Don't want to be scrambling at the end.
upvoted 0 times
Nichelle
10 days ago
C) As Late As Possible could work if there are no dependencies between the tasks.
upvoted 0 times
...
Nelida
17 days ago
I think B) Must Start On might be better to ensure the tasks are completed on time.
upvoted 0 times
...
Nieves
24 days ago
I agree, A) Start No Later Than is a good choice. It allows for some flexibility.
upvoted 0 times
...
...
Andrew
2 months ago
Definitely B) Must Start On. You can't leave these critical tasks to the last minute, you know. Gotta be organized!
upvoted 0 times
Brendan
15 days ago
Using Must Start On will give the team a clear target to work towards in the final days of the project.
upvoted 0 times
...
Reena
18 days ago
I think it's important to have a clear deadline for those final tasks to avoid any last-minute rush.
upvoted 0 times
...
Frederick
1 months ago
Yeah, setting a specific start date for those tasks will help keep everything on track.
upvoted 0 times
...
Paz
1 months ago
I agree, B) Must Start On is the best option to ensure those tasks are completed on time.
upvoted 0 times
...
...
Franklyn
2 months ago
I think the answer should be C) As Late As Possible. That way the project manager can squeeze out the last bit of time before the deadline.
upvoted 0 times
Ines
1 months ago
But wouldn't A) Start No Later Than also work? It ensures we start those tasks early enough to finish on time.
upvoted 0 times
...
Hillary
1 months ago
I agree, C) As Late As Possible would give us the flexibility we need to finish those tasks right before the deadline.
upvoted 0 times
...
...

Save Cancel