The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
In Workfront, the 'As Late As Possible' task constraint ensures that tasks are scheduled as close to the project's end date as possible. This is useful when specific start dates are not necessary, but tasks need to happen near the end of the project timeline. This constraint allows for flexibility while still ensuring that the tasks are completed within the required time frame.
Sena
2 months agoVeronika
2 months agoLynelle
1 months agoChaya
1 months agoMelina
1 months agoAshton
1 months agoYun
1 months agoGearldine
2 months agoMichal
2 months agoValene
2 months agoMila
3 months agoHoa
3 months agoNichelle
1 months agoNelida
2 months agoNieves
2 months agoAndrew
3 months agoBrendan
2 months agoReena
2 months agoFrederick
2 months agoPaz
2 months agoFranklyn
3 months agoInes
2 months agoHillary
2 months ago