As part of a large scale marketing campaign, an activity must run for 10 days. It will start at 3:00 am on a specific date and end 10 days later at 3:00 am. What is the easiest way to ensure this activity starts and ends automatically?

Show Suggested Answer Hide Answer
Suggested Answer: B