Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe Exam AD0-E406 Topic 6 Question 20 Discussion

Actual exam question for Adobe's AD0-E406 exam
Question #: 20
Topic #: 6
[All AD0-E406 Questions]

As part of a large scale marketing campaign, an activity must run for 10 days. It will start at 3:00 am on a specific date and end 10 days later at 3:00 am. What is the easiest way to ensure this activity starts and ends automatically?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel