You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.
All of the following are characteristics of standard normal distribution, except:
The statement that the 'means and median are not equal' is incorrect for a standard normal distribution. In a standard normal distribution, the mean, median, and mode are all equal, as the distribution is perfectly symmetrical. The correct characteristics of a standard normal distribution are that approximately 68% of the values fall within one standard deviation of the mean, the total area under the curve is 1, and the curve shape is symmetrical.
The measure of number of units completed divided by work-hours consumed is referred to as:
Productivity is defined as the measure of the number of units completed divided by the work-hours consumed. It is a key performance indicator in construction and other project-based industries, reflecting how efficiently resources are being used to produce outputs.
Key Points:
Productivity Calculation:
Productivity = Number of units completed / Work-hours consumed.
Higher productivity means more output is being generated per unit of time, indicating efficient use of resources.
Other Terms:
Lined Value: Not a standard term related to productivity.
Credit Work-Hours: A concept related to earned work-hours, not a direct measure of productivity.
Cost Performance Index (CPI): A measure in earned value management indicating the cost efficiency of budgeted resources, calculated as EV/AC.
Conclusion: The correct answer is C. Productivity because it directly refers to the efficiency of labor in terms of output per work-hour.
Which of the following is used for measuring productivity loss?
Productivity loss in projects, particularly in construction, can be measured using various methods. The Earned Value Management (EVM) system includes the Earned Formula to compare the work performed against the work planned.
Key Points:
Earned Formula:
This formula is used in EVM to calculate key performance indicators like the Cost Performance Index (CPI) and Schedule Performance Index (SPI), which help in understanding productivity loss.
By comparing earned value (the work actually performed) against planned value, project managers can assess whether the project is behind or ahead in terms of schedule and budget, indirectly measuring productivity loss.
Other Options:
Central Limit Theorem: This is a statistical concept, not directly used for measuring productivity loss.
Value Engineering: A process that seeks to improve the value of goods or products by using an examination of function, not directly related to measuring productivity loss.
Conclusion: The correct answer is C. Earned formula because it is directly linked to measuring productivity loss in project management through the EVM system.
Which of the following is NOT an advantage specific to a cost reimbursable contract?
In a cost reimbursable contract, the contractor is reimbursed for all allowable costs incurred during the project, plus an additional fee (which could be a fixed fee or a percentage of costs). This contract type provides several advantages but also has its limitations.
Key Points:
Advantages of Cost Reimbursable Contracts:
Simpler Proposal Evaluation: The focus is on selecting the best contractor rather than the lowest bid, making the evaluation process simpler.
Flexibility in Dealing with Changes: This contract type allows for adjustments and changes as the project progresses.
Early Start: Work can begin quickly without needing a fully defined scope since costs are reimbursed.
Owner Control:
While cost reimbursable contracts offer flexibility, they do not inherently mean that the owner controls all aspects of the work. The contractor typically manages the execution of the project, while the owner retains control over the budget and major decisions.
Conclusion: The correct answer is D. Owner controls all aspects of the work because, in cost reimbursable contracts, the contractor has significant control over how the work is performed, while the owner mainly controls costs and high-level decisions.
Antonio
9 days agoErick
20 days agoLon
24 days agoBrandee
1 months agoRhea
2 months agoHermila
2 months agoBarb
2 months agoAdell
3 months agoValda
3 months agoNichelle
3 months agoKeneth
3 months agoEarnestine
3 months agoJudy
4 months ago