What changes to logic would eliminate Activity B from the critical path?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Omer
8 days agoSimona
1 months agoJohnathon
1 months agoAlex
2 months agoMerri
2 months agoTamra
3 months agoMadonna
3 months agoNovella
3 months agoNelida
4 months agoJamal
4 months agoHassie
4 months agoGlenna
5 months agoMa
5 months agoKeneth
5 months agoMaryln
6 months agoKenny
6 months agoStevie
6 months agoMozelle
6 months agoCharisse
7 months agoMila
8 months agoMozell
8 months agoNakisha
9 months agoShonda
9 months agoGayla
9 months agoScarlet
10 months agoShasta
11 months ago