If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
Determine the correct formula and date for the late finish for Activity 6002.
What changes to logic would eliminate Activity B from the critical path?
What day would Activity C complete if the duration of Activity A was reduced by five days?
Chan
23 days agoOmer
2 months agoSimona
3 months agoJohnathon
3 months agoAlex
4 months agoMerri
4 months agoTamra
4 months agoMadonna
5 months agoNovella
5 months agoNelida
5 months agoJamal
6 months agoHassie
6 months agoGlenna
6 months agoMa
7 months agoKeneth
7 months agoMaryln
7 months agoKenny
7 months agoStevie
7 months agoMozelle
8 months agoCharisse
9 months agoMila
10 months agoMozell
10 months agoNakisha
10 months agoShonda
10 months agoGayla
11 months agoScarlet
12 months agoShasta
1 years ago