BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 5 Question 7 Discussion

Actual exam question for AACE International's CCP exam
Question #: 7
Topic #: 5
[All CCP Questions]

You are reporting the following Earned Value Analysis information for the project:

EV= $1,500,000

AC=$1.000,000

PV= $2,000,000

What is the status of the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The problem provides key metrics used in Earned Value Management (EVM):

Earned Value (EV): $1,500,000

Actual Cost (AC): $1,000,000

Planned Value (PV): $2,000,000

Key Points:

Schedule Performance Index (SPI):

SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75

An SPI less than 1 indicates the project is behind schedule.

Cost Performance Index (CPI):

CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5

A CPI greater than 1 indicates the project is under budget.

Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.


Contribute your Thoughts:

Osvaldo
1 months ago
Looks like the project manager is trying to pull a fast one on us. If the EV is less than the PV, that means we're behind schedule. And if the AC is higher than the EV, well, we're over budget. Option B all the way, my dude!
upvoted 0 times
...
Ronny
1 months ago
I'm feeling a bit like a budget detective here. Let's see, if the EV is less than the PV, we're behind schedule. And if the AC is higher than the EV, we're over budget. Definitely option B, no doubt about it!
upvoted 0 times
Solange
20 days ago
Looks like we need to make some adjustments to get back on track.
upvoted 0 times
...
Merilyn
22 days ago
Yes, I agree. The project is behind schedule and over budget.
upvoted 0 times
...
Peggy
26 days ago
I think option B is the correct one.
upvoted 0 times
...
...
Brigette
1 months ago
Hold up, let me put on my project management glasses. Okay, got it! Since the EV is less than the PV, we're behind schedule. And the AC is higher than the EV, so we're over budget. B is the way to go.
upvoted 0 times
Benton
19 days ago
B) Project is behind schedule, but over budget
upvoted 0 times
...
Rasheeda
1 months ago
AC is higher than EV, so we're over budget.
upvoted 0 times
...
Kimi
1 months ago
EV is less than PV, so we're behind schedule.
upvoted 0 times
...
...
Glory
2 months ago
So, the answer is B) Project is behind schedule, but over budget.
upvoted 0 times
...
Long
2 months ago
I agree, the PV is higher than EV.
upvoted 0 times
...
Venita
2 months ago
Woah, this is a tricky one! If the project's EV is less than the PV, that means we're behind schedule. And if the AC is more than the EV, we're over budget. Gotta be option B, my friend.
upvoted 0 times
...
Felicidad
2 months ago
Hmm, let's see. The project's EV is $1,500,000, AC is $1,000,000, and PV is $2,000,000. Looks like we're behind schedule, but over budget. I'd go with option B.
upvoted 0 times
An
1 months ago
Yes, it looks like the project is behind schedule and over budget. Option B is the best choice.
upvoted 0 times
...
Aja
1 months ago
I agree, option B seems to be the most accurate based on the information provided.
upvoted 0 times
...
...
Eliseo
2 months ago
I think the project is behind schedule.
upvoted 0 times
...

Save Cancel