You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Osvaldo
6 months agoRonny
7 months agoSolange
6 months agoMerilyn
6 months agoPeggy
6 months agoBrigette
7 months agoBenton
6 months agoRasheeda
6 months agoKimi
6 months agoGlory
7 months agoLong
7 months agoVenita
7 months agoFelicidad
7 months agoAn
6 months agoAja
6 months agoEliseo
7 months ago