You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
The problem provides key metrics used in Earned Value Management (EVM):
Earned Value (EV): $1,500,000
Actual Cost (AC): $1,000,000
Planned Value (PV): $2,000,000
Key Points:
Schedule Performance Index (SPI):
SPI = EV / PV = $1,500,000 / $2,000,000 = 0.75
An SPI less than 1 indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC = $1,500,000 / $1,000,000 = 1.5
A CPI greater than 1 indicates the project is under budget.
Conclusion: The correct answer is C. Project is behind schedule, but under budget because the SPI indicates a delay in schedule, and the CPI shows that the project is currently spending less than planned.
Osvaldo
1 months agoRonny
1 months agoSolange
20 days agoMerilyn
22 days agoPeggy
26 days agoBrigette
1 months agoBenton
19 days agoRasheeda
1 months agoKimi
1 months agoGlory
2 months agoLong
2 months agoVenita
2 months agoFelicidad
2 months agoAn
1 months agoAja
1 months agoEliseo
2 months ago